Collins Project Management is now a Darden Company!
Click Here for More Info
The Galloway School 2019-02-22T20:03:53+00:00

Fine Arts Center

The Galloway School

Location: Atlanta, Georgia

Date Completed: 2003

Project Cost: $10 million

Construction Cost: $7 million

Architect: Gardner Spencer Smith

General Contractor: Choate Construction Company

Collins Project Management was engaged to provide total program management services from concept through completion and occupancy. The project consisted of a 40,000 sf, 300-seat Theater, Classroom Addition, covered parking, and playground.

The Fine Arts Center had to be carefully planned and staged to minimize impact on ongoing school operations. Communication with adjacent neighborhoods was critical to success because of the sensitivities of the surrounding community to construction traffic, noise and dust.

The project team had to navigate a difficult project approval and permitting process, and then maintain an aggressive construction schedule in order to complete the project and make it available for the school year.

“The Galloway School is thankful that we made the decision to engage Collins Project Management to represent us on our Fine Arts Center Project. Not only did you provide excellent professional and technical skills in managing the lengthy process, but all of your staff involved worked so very well with the rest of the development team. I am convinced that this resulted in the best possible positive experience for all parties when that is not always the outcome in a challenging project such as ours. I am confident that our current athletic complex project will prove to be a similar experience. Thanks again for all that you do to make our projects a success.”
Terry Tracy, Director of Finance